Passavant ER

Passavant Emergency Addition

B&A  provided civil/site services including topographic and property surveys, subsurface utility locating and surveying, site grading, landscaping, parking area lighting, site utilities, parking areas, traffic movements, ambulance drive, entrance loading/unloading area, retaining walls and ADA accessibility.

B&A also prepared stage demolition and construction plans to allow the existing facility to remain operational throughout the construction of the new addition.

Size

22,000 SF

Funding

Passavant Area Hospital

Cost

$11 million

Client

Passavant Area Hospital – Jacksonville, IL

Waynesville Bridge

Flood Study and Bridge

Evaluation of major flood event, recommendations to mitigate future flooding, design and construction phase engineering of a new bridge.

Funding

Flood Study – City Funds
Bridge Construction – FEMA Hazard Mitigation Grant/City Funds

Cost

Flood Study – $75,600
Bridge Construction – $315,000

Client

City of Waynesville, Missouri

Eagle Creek Park

Eagle Creek State Park

The Eagle Creek improvement project consisted of multiple sidewalks, a large patio area, a landscape block retaining wall, access to the patio with steps as well as an ADA vertical lift, and 57 boat slips with electrical hookups and ADA accessibility.

Funding

State of Illinois (CDB/IDNR)

Cost

$1,750,000

Client

Capital Development Board and Illinois Department of Natural Resources (Using Agency)

MacMurray College Football Field and Track

Football Field and Track

This project provided civil/site services included new home bleachers and press box and the relocation of home bleachers. There was also extensive grading of the banks to improve maintenance and aesthetics.

Funding

MacMurray College funds
Alumni donations
Illinois Legislative Initiative Grant

Cost

$750,000

Client

MacMurray College – Jacksonville, IL

IC Bruner Rec Center

Bruner Fitness and Recreation Center

Civil/site services that included solutions for underground storage for excess storm water runoff, support utilities, a sanitary sewer service, grading for 2 separate entrances, parking facilities, landscaping and a plaza area.

Size

150,000 S.F.

Funding

Illinois College Funds

Cost

$23,000,000

Project Duration

20 months

Client

Illinois College – Jacksonville, Illinois

Weaver Medical

Weaver Medical

Development of two (2) professional office buildings.

  • Surveying
  • Prepared site layout including water distribution mains
  • Relocation of the existing sanitary sewer mains that were in conflict with the proposed buildings and service connections to the main
  • Storm water collection and retention
  • Parking lot layout and design
  • Landscaping

Funding

Private

Client

Weaver Holdings – Kirksville, Missouri

Buchanan and Cody Funeral Home

Buchanan & Cody

This project consisted of topographic and boundary survey to provide a base map for design. Final design included construction plans and technical specification for providing parking for 161 vehicles, site lighting and landscaping, sidewalks, site entrances and erosion control.

Cost

$2.3 Million

Funding

Private

Client

Buchanan & Cody Funeral Homes, Jacksonville, Illinois

ATSU Kirksville

A.T. Still University

Site/civil services for a new dental school for A.T. Still University.

Duration

24 months

Funding

A.T. Still University

Cost

$17.2 Million

Client

A.T. Still University – Kirksville, Missouri

McDonough District Hospital Emergency Room Entrance

MDH Emergency Wing

B&A was involved in the construction of concrete parking, re-construction of the perimeter roadway, new storm and sanitary sewer, water services, relocation of the helicopter landing pad, and detention pond design.

Size

45,000 SF

Funding

McDonough District Hospital

Cost

$32,000,000

Client

McDonough District Hospital